The Champions Drive project completion is expected to be mid-May.  This is great news!  Here are the highlights:

  • The project is 98.93% complete
  • Sidewalk/Trail completed this week
  • New upgrade signal at FM 1960 & Champions Drive estimated completion by April 6th
  • Grading for drainage tied to storm sewer system estimated completion by April 6th
  • Landscaping estimated completion by May 11th
  • Road striping, new street signs, speed limit signs and other signage estimated completion by May 11th
  • Landscape irrigation booster pumps – working on

Project updates are posted on the Champions MUD website: www.championswater.com    

If you have questions regarding the construction project, please direct inquiries to COMMUNITY ASSISTANCE DIRECTOR office of PCT 4, COMMISSIONER, Jack Cagle at cadir@hcp4.net. You may also visit their website by clicking HERE.

 

| Categories: Community News & Announcements | Tags: | View Count: (540) | Return
Search
Categories
Archive

Champions Community Improvement Association

About Champions

The Champion’s community has much to offer families looking for a new place to call home. What began in the 1960’s as an exclusive golfing community has expanded into a neighborhood of over 800 homes sprawled out over prime real estate divided into distinct sections ranging from new custom homes to mature homes many of which are on the golf course or situated around the Champions Lake. MORE

Champions News
Contact Us

Mailing Address
5315-B Cypress Creek Pkwy, #185
Houston, TX  77069
281-397-2200 Voicemail
281-580-4820 Fax